CASE STUDY #3111

Bus Depot for Swan Group and the Public Transport Authority

Bus Depot for Swan Group and the Public Transport Authority

16 AUGUST 2023 Case Study # 3111
PROJECT VALUE: $1M - $1.2M
PROJECT BUILD TIME: 8 WORKING WEEKS ON SITE, 28 WEEKS TOTAL

CLIENT BRIEF

The requirement for a new Transperth bus depot facility was identified, and this included an administration office, workshop, bus parking and car parking areas. This was a project we were contracted to by our partners Swan Group for the Public Transport Authority (the PTA is responsible for WA’s rail, bus, ferry, and coach networks in both metro and regional areas).

CHALLENGES

AUSPAN SOLUTIONS

FEATURES

  • Collaborating with a variety of consultants and the principal’s architect to create an architecturally designed building in all aspects.
  • Engineered roof lift design to eliminate working at heights on the workshop roof.
  • Practical and efficient design.

CLIENT TESTIMONIAL

AUSPAN TESTIMONIAL

What Are you waiting for?

Your Shed Construction Simplified,
Delivered On Time, and Created Uniquely for Your Needs.

image (1)-1
RUSSEL MILLER COMMERCIAL BUILDING MANAGER